All industries › Utility solar › North Carolina › Apple Data Center - PV2

Utility solar illustration Utility solar · Catawba County, North Carolina

Apple Data Center - PV2

A 20 MW utility solar project in Catawba County, North Carolina. Apple Data Center - PV2 is built and in service. Public records name Apple as its developer. No public record read so far names its builder.

The record

What the public record says about Apple Data Center - PV2, as of 22 Oct 2026.

StageOperating
Construction startIn service since 2013
Size20 MW
LocationCatawba County, North Carolina (to about 10 km)
DeveloperApple
Grid operator—
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Apple

ProjectStageSize
MDN.06Data centers · Catawba County, North CarolinaUnder construction—
Project Morgan Apple Inc. Data CenterData centers · Dallas County, IowaUnder construction642 acres
Apple Data CenterData centers · Crook County, OregonPre-construction—
Apple Data CenterData centers · ArizonaPre-construction—
Apple Data Center PVUtility solar · Catawba County, North CarolinaOperating21 MW
Apple Data Center PV3Utility solar · Catawba County, North CarolinaOperating18 MW

Every Apple project

Also in Catawba County

ProjectStageSize
Maiden Creek BatteryBattery storageUnder construction50 MW
CLT04 Lyle Creek Data CenterData centersUnder construction—
CLT10 Boyd Farms Data CenterData centersUnder construction—
CLT17 Stover Data CenterData centersUnder construction—
MDN.06Data centersUnder construction—
CLT40 Data CenterData centersPre-construction—

Every project in Catawba County

More

Questions

Apple Data Center - PV2, in short.

Where is Apple Data Center - PV2?

Apple Data Center - PV2 is a 20 MW utility solar project in Catawba County, North Carolina. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Apple Data Center - PV2?

Apple Data Center - PV2 is built and in service since 2013.

Who is developing Apple Data Center - PV2?

Apple, as the public record names it.

Who is building Apple Data Center - PV2?

No public record read so far names a builder for Apple Data Center - PV2. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.