A 120 MW utility solar project in San Bernardino County, California. Aratina Solar Center 1A is built and in service. Public records name 64NB 8me LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Aratina Solar Center 1A, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2026 |
| Size | 120 MW |
| Location | San Bernardino County, California (to about 10 km) |
| Developer | 64NB 8me LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- A filing dates the construction start to September 2023.
- Stormwater permit filed.
Who was named on it, and when, is in the app.
Also in San Bernardino County
| Project | Stage | Size |
|---|---|---|
| Vidal Energy CenterUtility solar | Under construction | 160 MW |
| OVERNIGHT SOLARUtility solar | Under construction | 150 MW |
| BALDY MESA 2Utility solar | Under construction | 50 MW |
| Baldy Mesa StorageBattery storage | Under construction | 50 MW |
| CONDUIT ENERGY STORAGEBattery storage | Financed | 513 MW |
| TROLLEYBattery storage | Financed | 406 MW |
More
Questions
Aratina Solar Center 1A, in short.
Where is Aratina Solar Center 1A?
Aratina Solar Center 1A is a 120 MW utility solar project in San Bernardino County, California. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Aratina Solar Center 1A?
Aratina Solar Center 1A is built and in service since 2026.
Who is developing Aratina Solar Center 1A?
64NB 8me LLC, as the public record names it.
Who is building Aratina Solar Center 1A?
No public record read so far names a builder for Aratina Solar Center 1A. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.