Arlington Energy Center II
A 233 MW utility solar project in Riverside County, California. Arlington Energy Center II is built and in service. Public records name Arlington Energy Center II as its developer. No public record read so far names its builder.
The record
What the public record says about Arlington Energy Center II, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2022 |
| Size | 233 MW |
| Location | Riverside County, California (to about 10 km) |
| Developer | Arlington Energy Center II |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also in Riverside County
| Project | Stage | Size |
|---|---|---|
| GRACE ENERGY CENTERUtility solar | Under construction | 509 MW |
| ATHOS POWER PLANTUtility solar | Under construction | 450 MW |
| SE Athos IIBattery storage | Under construction | 402 MW |
| EASLEYUtility solar | Under construction | 290 MW |
| COBALTUtility solar | Under construction | 256 MW |
| DOUBLE BUTTE STORAGEBattery storage | Financed | 508 MW |
More
Questions
Arlington Energy Center II, in short.
Where is Arlington Energy Center II?
Arlington Energy Center II is a 233 MW utility solar project in Riverside County, California. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Arlington Energy Center II?
Arlington Energy Center II is built and in service since 2022.
Who is developing Arlington Energy Center II?
Arlington Energy Center II, as the public record names it.
Who is building Arlington Energy Center II?
No public record read so far names a builder for Arlington Energy Center II. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.