All industries › Battery storage › Ohio › Bowling Green Energy Storage Project

Battery storage illustration Battery storage · Wood County, Ohio

Bowling Green Energy Storage Project

A 12 MW battery storage project in Wood County, Ohio. Bowling Green Energy Storage Project is built and in service. Public records name VESI 21 LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Bowling Green Energy Storage Project, as of 25 Oct 2026.

StageOperating
Construction startIn service since 2023
Size12 MW
LocationWood County, Ohio (to about 10 km)
DeveloperVESI 21 LLC
Grid operator—
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also in Wood County

ProjectStageSize
Juliet EnergyUtility solarUnder construction50 MW
First Solar PGT-04Utility solarUnder construction—
Oppidan Bowling Green Data CenterData centersUnder construction—
Unnamed 950 MW storage projectBattery storageQueued950 MW
Unnamed 300 MW solar projectUtility solarQueued300 MW
Unnamed 300 MW solar projectUtility solarQueued300 MW

Every project in Wood County

More

Questions

Bowling Green Energy Storage Project, in short.

Where is Bowling Green Energy Storage Project?

Bowling Green Energy Storage Project is a 12 MW battery storage project in Wood County, Ohio. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Bowling Green Energy Storage Project?

Bowling Green Energy Storage Project is built and in service since 2023.

Who is developing Bowling Green Energy Storage Project?

VESI 21 LLC, as the public record names it.

Who is building Bowling Green Energy Storage Project?

No public record read so far names a builder for Bowling Green Energy Storage Project. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $1,500 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.