All industries › Utility solar › Texas › Brazoria County Solar Project (Danciger)
Utility solar · Brazoria County, Texas
Brazoria County Solar Project (Danciger)
A 200 MW utility solar project in Brazoria County, Texas. Brazoria County Solar Project (Danciger) is built and in service. Public records name Brazoria County Solar Project, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Brazoria County Solar Project (Danciger), as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2022 |
| Size | 200 MW |
| Location | Brazoria County, Texas (to about 10 km) |
| Developer | Brazoria County Solar Project, LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also developed by Brazoria County Solar Project, LLC
| Project | Stage | Size |
|---|---|---|
| Danciger SolarUtility solar · Brazoria County, Texas | Operating | 203 MW |
Also in Brazoria County
| Project | Stage | Size |
|---|---|---|
| Cottonwood Bayou SolarUtility solar | Under construction | 351 MW |
| Myrtle SolarUtility solar | Under construction | 321 MW |
| Tanglewood SolarUtility solar | Under construction | 251 MW |
| Brazoria Solar IUtility solar | Under construction | 250 MW |
| Cradle SolarUtility solar | Under construction | 201 MW |
| CastorBattery storage | Under construction | 200 MW |
More
Questions
Brazoria County Solar Project (Danciger), in short.
Where is Brazoria County Solar Project (Danciger)?
Brazoria County Solar Project (Danciger) is a 200 MW utility solar project in Brazoria County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Brazoria County Solar Project (Danciger)?
Brazoria County Solar Project (Danciger) is built and in service since 2022.
Who is developing Brazoria County Solar Project (Danciger)?
Brazoria County Solar Project, LLC, as the public record names it.
Who is building Brazoria County Solar Project (Danciger)?
No public record read so far names a builder for Brazoria County Solar Project (Danciger). Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.