What the public record says about Cattlemen Solar II, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q1 2025 estimate |
| Size | 200 MW |
| Location | Milam County, Texas (to about 10 km) |
| Developer | Cattlemen Solar Park II LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also developed by Cattlemen Solar Park II LLC
| Project | Stage | Size |
|---|---|---|
| Eastbell Milam Solar IIUtility solar · Milam County, Texas | Under construction | 151 MW |
Also in Milam County
| Project | Stage | Size |
|---|---|---|
| Sypert Branch Solar ProjectUtility solar | Under construction | 261 MW |
| Eastbell Milam SolarUtility solar | Under construction | 245 MW |
| Cattlemen Solar ParkUtility solar | Under construction | 240 MW |
| Hoyte SolarUtility solar | Under construction | 207 MW |
| Yaupon Solar SLFUtility solar | Under construction | 201 MW |
| Camino Santiago SolarUtility solar | Under construction | 196 MW |
More
Questions
Cattlemen Solar II, in short.
Where is Cattlemen Solar II?
Cattlemen Solar II is a 200 MW utility solar project in Milam County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Cattlemen Solar II?
Groundtrace estimates construction started in the first quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Cattlemen Solar II?
Cattlemen Solar Park II LLC, as the public record names it.
Who is building Cattlemen Solar II?
No public record read so far names a builder for Cattlemen Solar II. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.