All industries › Utility solar › Arizona › Centennial Flats
Utility solar · La Paz County, Arizona
Centennial Flats
A 167 MW utility solar project in La Paz County, Arizona. Centennial Flats has work under way on site. Public records name Copia Power as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Centennial Flats, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q2 2024 permit on file |
| Size | 167 MW |
| Location | La Paz County, Arizona (to about 10 km) |
| Developer | Copia Power |
| Grid operator | — |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Grading seen on site from satellite.
- Satellite imagery shows first ground work on site.
- Clearing seen on site from satellite.
Who was named on it, and when, is in the app.
Also developed by Copia Power
| Project | Stage | Size |
|---|---|---|
| Harquahala 2Utility solar · Maricopa County, Arizona | Operating | 300 MW |
| Harquahala Sun Solar ProjectUtility solar · Maricopa County, Arizona | Operating | 150 MW |
Also in La Paz County
| Project | Stage | Size |
|---|---|---|
| Atlas VIIIBattery storage | Under construction | 382 MW |
| AtlasUtility solar | Under construction | 300 MW |
| ATLAS SOLAR IVUtility solar | Under construction | 300 MW |
| Atlas BESS IVBattery storage | Under construction | 150 MW |
| ATLAS IIUtility solar | Under construction | 100 MW |
| ATLAS Solar VIUtility solar | Under construction | 100 MW |
More
Questions
Centennial Flats, in short.
Where is Centennial Flats?
Centennial Flats is a 167 MW utility solar project in La Paz County, Arizona. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Centennial Flats?
A construction permit on file dates the start of work to the second quarter of 2024.
Who is developing Centennial Flats?
Copia Power, as the public record names it.
Who is building Centennial Flats?
A builder is named for Centennial Flats in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.