All industries › Utility solar › Idaho › Crimson Orchard Solar and BESS

Utility solar illustration Utility solar · Elmore County, Idaho

Crimson Orchard Solar and BESS

A 100 MW utility solar project in Elmore County, Idaho. Crimson Orchard Solar and BESS has work under way on site. Public records name Clenera DevCo LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Crimson Orchard Solar and BESS, as of 22 Oct 2026.

StageUnder construction
Construction startQ1 2022 permit on file
Size100 MW
LocationElmore County, Idaho (to about 10 km)
DeveloperClenera DevCo LLC
Grid operator—
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

  1. Entered the public record for the first time.

Who was named on it, and when, is in the app.

Also developed by Clenera DevCo LLC

ProjectStageSize
Snowflake A Solar and BESSUtility solar · Navajo County, ArizonaUnder construction475 MW
CO Bar Solar and BESSUtility solar · Coconino County, ArizonaUnder construction400 MW
CO Bar D Solar and BESSUtility solar · Coconino County, ArizonaUnder construction394 MW
Country Acres Clean PowerUtility solar · Placer County, CaliforniaUnder construction344 MW
CO Bar C Solar and BESSUtility solar · Coconino County, ArizonaUnder construction206 MW
Coggon SolarUtility solar · Linn County, IowaUnder construction100 MW

Every Clenera DevCo LLC project

Also in Elmore County

ProjectStageSize
IP request 667Utility solarFinanced400 MW
IP request 590Utility solarFinanced330 MW
IP request 551Utility solarFinanced240 MW
IP request 605Utility solarFinanced240 MW
IP request 636Utility solarFinanced149 MW
IP request 604Utility solarFinanced100 MW

Every project in Elmore County

More

Questions

Crimson Orchard Solar and BESS, in short.

Where is Crimson Orchard Solar and BESS?

Crimson Orchard Solar and BESS is a 100 MW utility solar project in Elmore County, Idaho. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Crimson Orchard Solar and BESS?

A construction permit on file dates the start of work to the first quarter of 2022.

Who is developing Crimson Orchard Solar and BESS?

Clenera DevCo LLC, as the public record names it.

Who is building Crimson Orchard Solar and BESS?

No public record read so far names a builder for Crimson Orchard Solar and BESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.