All industries › Utility solar › Florida › Debary Solar Power Plant

Utility solar illustration Utility solar · Volusia County, Florida

Debary Solar Power Plant

A 74 MW utility solar project in Volusia County, Florida. Debary Solar Power Plant is built and in service. Public records name Duke Energy Florida, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Debary Solar Power Plant, as of 25 Oct 2026.

StageOperating
Construction startIn service since 2020
Size74 MW
LocationVolusia County, Florida (to about 10 km)
DeveloperDuke Energy Florida, LLC
Grid operator—
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

  1. A filing dates the construction start to December 2015.
  2. Stormwater permit filed.

Who was named on it, and when, is in the app.

Also developed by Duke Energy Florida, LLC

ProjectStageSize
Powerline Energy StorageBattery storage · Citrus County, FloridaUnder construction100 MW
Duke request 322Utility solar · Sumter County, FloridaUnder construction75 MW
Duke request 323Utility solar · Jackson County, FloridaUnder construction75 MW
Duke request 325Utility solar · Osceola County, FloridaUnder construction75 MW
Duke request 326Utility solar · Osceola County, FloridaUnder construction75 MW
Duke request 341Utility solar · Orange County, FloridaUnder construction75 MW

Every Duke Energy Florida, LLC project

Also in Volusia County

ProjectStageSize
Pioneer Trail Solar Energy CenterUtility solarOperating74 MW
Daytona International Speedway SolarUtility solarOperating2 MW

More

Questions

Debary Solar Power Plant, in short.

Where is Debary Solar Power Plant?

Debary Solar Power Plant is a 74 MW utility solar project in Volusia County, Florida. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Debary Solar Power Plant?

Debary Solar Power Plant is built and in service since 2020.

Who is developing Debary Solar Power Plant?

Duke Energy Florida, LLC, as the public record names it.

Who is building Debary Solar Power Plant?

No public record read so far names a builder for Debary Solar Power Plant. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $1,500 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.