All industries › Utility solar › Florida › Duke request 151
Utility solar · Columbia County, Florida
Duke request 151
A 74 MW utility solar project in Columbia County, Florida. Duke request 151 has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Duke Energy Florida, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Duke request 151, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Not dated or estimated yet |
| Size | 74 MW |
| Location | Columbia County, Florida (to about 10 km) |
| Developer | Duke Energy Florida, LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also developed by Duke Energy Florida, LLC
| Project | Stage | Size |
|---|---|---|
| Powerline Energy StorageBattery storage · Citrus County, Florida | Under construction | 100 MW |
| Bailey Mill SolarUtility solar · Jefferson County, Florida | Under construction | 75 MW |
| Duke request 322Utility solar · Sumter County, Florida | Under construction | 75 MW |
| Duke request 323Utility solar · Jackson County, Florida | Under construction | 75 MW |
| Duke request 325Utility solar · Osceola County, Florida | Under construction | 75 MW |
| Duke request 326Utility solar · Osceola County, Florida | Under construction | 75 MW |
Also in Columbia County
| Project | Stage | Size |
|---|---|---|
| Columbia Solar Power PlantUtility solar | Operating | 75 MW |
| Santa Fe Solar Power PlantUtility solar | Operating | 75 MW |
| Columbia County SolarUtility solar | Operating | 74 MW |
| Price CreekUtility solar | Operating | 74 MW |
| Sunshine Gateway Solar Energy CenterUtility solar | Operating | 74 MW |
More
Questions
Duke request 151, in short.
Where is Duke request 151?
Duke request 151 is a 74 MW utility solar project in Columbia County, Florida. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Duke request 151?
No record dates the construction start yet, and Groundtrace has not estimated one.
Who is developing Duke request 151?
Duke Energy Florida, LLC, as the public record names it.
Who is building Duke request 151?
No public record read so far names a builder for Duke request 151. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.