All industries › Utility solar › New Jersey › Gloucester
Utility solar · Camden County, New Jersey
Gloucester
A 2 MW utility solar project in Camden County, New Jersey. Gloucester is built and in service. Public records name Altus Power America Management, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Gloucester, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2019 |
| Size | 2 MW |
| Location | Camden County, New Jersey (to about 10 km) |
| Developer | Altus Power America Management, LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Altus Power America Management, LLC
| Project | Stage | Size |
|---|---|---|
| SunEast Dog Corners Solar ProjectUtility solar · Cayuga County, New York | Under construction | 20 MW |
| SunEast Flat Hill Solar ProjectUtility solar · Herkimer County, New York | Under construction | 20 MW |
| SunEast Valley Solar ProjectUtility solar · Tioga County, New York | Under construction | 20 MW |
| Ellis SolarUtility solar · Tompkins County, New York | Operating | 18 MW |
| Searchlight SolarUtility solar · Clark County, Nevada | Operating | 18 MW |
| Pasto SolarUtility solar · Tioga County, New York | Operating | 16 MW |
Also in Camden County
| Project | Stage | Size |
|---|---|---|
| Unnamed 300 MW storage projectBattery storage | Queued | 300 MW |
| Unnamed 300 MW storage projectBattery storage | Queued | 300 MW |
| Unnamed 29 MW solar projectUtility solar | Queued | 29 MW |
| Pennsauken Brownfield SolarUtility solar | Operating | 12 MW |
| Riverside Renewable EnergyUtility solar | Operating | 8 MW |
| DRPA Lindenwold Station Solar ProjectUtility solar | Operating | 6 MW |
More
Questions
Gloucester, in short.
Where is Gloucester?
Gloucester is a 2 MW utility solar project in Camden County, New Jersey. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Gloucester?
Gloucester is built and in service since 2019.
Who is developing Gloucester?
Altus Power America Management, LLC, as the public record names it.
Who is building Gloucester?
No public record read so far names a builder for Gloucester. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.