A 200 MW utility solar project in Ada County, Idaho. IP request 567 is built and in service. Public records name Pleasant Valley Solar, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about IP request 567, as of 1 Nov 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2025 |
| Size | 200 MW |
| Location | Ada County, Idaho (to about 10 km) |
| Developer | Pleasant Valley Solar, LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also in Ada County
| Project | Stage | Size |
|---|---|---|
| IP request 665Utility solar | Under construction | 400 MW |
| IP request 669Utility solar | Financed | 200 MW |
| IP request 793Utility solar | Queued | 250 MW |
| IP request 710Utility solar | Queued | 200 MW |
| IP request 786Utility solar | Queued | 199 MW |
| IP request 708Utility solar | Queued | 150 MW |
More
Questions
IP request 567, in short.
Where is IP request 567?
IP request 567 is a 200 MW utility solar project in Ada County, Idaho. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on IP request 567?
IP request 567 is built and in service since 2025.
Who is developing IP request 567?
Pleasant Valley Solar, LLC, as the public record names it.
Who is building IP request 567?
No public record read so far names a builder for IP request 567. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.