A data center project in Butts County, Georgia. Legacy Trade Center - Lamar County, GA has filed for the permits that come just before ground work, such as construction stormwater coverage. Public records name Amazon Web Services as its developer. No public record read so far names its builder.

The record

What the public record says about Legacy Trade Center - Lamar County, GA, as of 23 Oct 2026.

StagePre-construction
Construction startQ2 2026 permit on file
SizeNot on record
LocationButts County, Georgia (to about 10 km)
DeveloperAmazon Web Services
Grid operator—
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Amazon Web Services

ProjectStageSize
Amazon Data Services Inc, Mceda Mega SiteData centers · Madison County, MississippiUnder construction—
Aws ATL 89Data centers · Newton County, GeorgiaUnder construction—
Aws Data Center Gilroy - SFO069Data centers · Santa Clara County, CaliforniaUnder construction—
Aws SFO090Data centers · CaliforniaUnder construction—
Cumulus Data CenterData centers · Luzerne County, PennsylvaniaUnder construction—
Icsp At Arcola And Evergreen Commerce Center Swm BData centers · Loudoun County, VirginiaUnder construction—

Every Amazon Web Services project

More

Questions

Legacy Trade Center - Lamar County, GA, in short.

Where is Legacy Trade Center - Lamar County, GA?

Legacy Trade Center - Lamar County, GA is a data center project in Butts County, Georgia. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Legacy Trade Center - Lamar County, GA?

A construction permit on file dates the start of work to the second quarter of 2026.

Who is developing Legacy Trade Center - Lamar County, GA?

Amazon Web Services, as the public record names it.

Who is building Legacy Trade Center - Lamar County, GA?

No public record read so far names a builder for Legacy Trade Center - Lamar County, GA. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.