A 10 MW battery storage project in Ector County, Texas. Non-PLD US-El Paso - BSSAT004 is built and in service. Public records name Prologis Logistics Services Incorporated BESS as its developer. No public record read so far names its builder.
The record
What the public record says about Non-PLD US-El Paso - BSSAT004, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2025 |
| Size | 10 MW |
| Location | Ector County, Texas (to about 10 km) |
| Developer | Prologis Logistics Services Incorporated BESS |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Prologis Logistics Services Incorporated BESS
| Project | Stage | Size |
|---|---|---|
| BESS TX Panda - BSHOU004Battery storage · Harris County, Texas | Operating | 10 MW |
| BESS TX Top Gear - BSHOU002Battery storage · Harris County, Texas | Operating | 10 MW |
| Century BESSBattery storage · Tarrant County, Texas | Operating | 10 MW |
| Citrus City BESSBattery storage · Hidalgo County, Texas | Operating | 10 MW |
| Crockett BESSBattery storage · Harris County, Texas | Operating | 10 MW |
| Liggett SwitchBattery storage · Tarrant County, Texas | Operating | 10 MW |
Also in Ector County
| Project | Stage | Size |
|---|---|---|
| Greyhound SolarUtility solar | Under construction | 335 MW |
| Cipher Mining Odessa Data CenterData centers | Under construction | 52 acres |
| Van Zandt Energy StorageBattery storage | Financed | 256 MW |
| Sisters SolarUtility solar | Financed | 101 MW |
| Gypsum Plains SolarUtility solar | Queued | 503 MW |
| Jackrabbit Flats SolarUtility solar | Queued | 401 MW |
More
Questions
Non-PLD US-El Paso - BSSAT004, in short.
Where is Non-PLD US-El Paso - BSSAT004?
Non-PLD US-El Paso - BSSAT004 is a 10 MW battery storage project in Ector County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Non-PLD US-El Paso - BSSAT004?
Non-PLD US-El Paso - BSSAT004 is built and in service since 2025.
Who is developing Non-PLD US-El Paso - BSSAT004?
Prologis Logistics Services Incorporated BESS, as the public record names it.
Who is building Non-PLD US-El Paso - BSSAT004?
No public record read so far names a builder for Non-PLD US-El Paso - BSSAT004. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.