All industries › Utility solar › New Mexico › TAG
Utility solar · Sandoval County, New Mexico
TAG
A 140 MW utility solar project in Sandoval County, New Mexico. TAG is built and in service. Public records name Exus New Mexico as its developer. No public record read so far names its builder.
The record
What the public record says about TAG, as of 22 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2025 |
| Size | 140 MW |
| Location | Sandoval County, New Mexico (to about 10 km) |
| Developer | Exus New Mexico |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Exus New Mexico
| Project | Stage | Size |
|---|---|---|
| Encino Solar Energy CenterUtility solar · Sandoval County, New Mexico | Operating | 55 MW |
| Britton Solar Energy CenterUtility solar · Torrance County, New Mexico | Operating | 50 MW |
| NMRD Data Center IIIUtility solar · Sandoval County, New Mexico | Operating | 50 MW |
| Facebook 1 Solar Energy CenterUtility solar · Valencia County, New Mexico | Operating | 10 MW |
| Facebook 2 Solar Energy CenterUtility solar · Bernalillo County, New Mexico | Operating | 10 MW |
| Facebook 3 Solar Energy CenterUtility solar · Bernalillo County, New Mexico | Operating | 10 MW |
Also in Sandoval County
| Project | Stage | Size |
|---|---|---|
| SLO-2Utility solar | Under construction | 5 MW |
| NMRD Data Center IVUtility solar | Financed | 140 MW |
| PNM request IA-PNM-2017-06Utility solar | Financed | 50 MW |
| PNM request IA-PNM-2017-07Utility solar | Financed | 50 MW |
| Encino Solar Energy CenterUtility solar | Operating | 55 MW |
| NMRD Data Center IIIUtility solar | Operating | 50 MW |
More
Questions
TAG, in short.
Where is TAG?
TAG is a 140 MW utility solar project in Sandoval County, New Mexico. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on TAG?
TAG is built and in service since 2025.
Who is developing TAG?
Exus New Mexico, as the public record names it.
Who is building TAG?
No public record read so far names a builder for TAG. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.