A 2 MW utility solar project in Hudson County, New Jersey. WEA Texas Bayonne is built and in service. Public records name Public Service Elec & Gas Co as its developer. No public record read so far names its builder.
The record
What the public record says about WEA Texas Bayonne, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2010 |
| Size | 2 MW |
| Location | Hudson County, New Jersey (to about 10 km) |
| Developer | Public Service Elec & Gas Co |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Public Service Elec & Gas Co
| Project | Stage | Size |
|---|---|---|
| Pennsauken Brownfield SolarUtility solar · Camden County, New Jersey | Operating | 12 MW |
| Cinnaminson Landfill SolarUtility solar · Burlington County, New Jersey | Operating | 10 MW |
| L&D Landfill SolarUtility solar · Burlington County, New Jersey | Operating | 10 MW |
| Kinsley Landfill SolarUtility solar · Gloucester County, New Jersey | Operating | 9 MW |
| Parkland Landfill SolarUtility solar · Burlington County, New Jersey | Operating | 8 MW |
| Kinsley II Landfill Solar SystemUtility solar · Gloucester County, New Jersey | Operating | 4 MW |
Also in Hudson County
| Project | Stage | Size |
|---|---|---|
| Bayonne Energy CenterBattery storage | Under construction | 50 MW |
| CoreSite NY4 Data CenterData centers | Pre-construction | — |
| Hudson Energy Storage FacilityBattery storage | Financed | 200 MW |
| Two Rivers StorageBattery storage | Financed | 150 MW |
| Railroad Avenue Energy StorageBattery storage | Queued | 10 MW |
| Ports Jersey City SolarUtility solar | Operating | 3 MW |
More
Questions
WEA Texas Bayonne, in short.
Where is WEA Texas Bayonne?
WEA Texas Bayonne is a 2 MW utility solar project in Hudson County, New Jersey. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on WEA Texas Bayonne?
WEA Texas Bayonne is built and in service since 2010.
Who is developing WEA Texas Bayonne?
Public Service Elec & Gas Co, as the public record names it.
Who is building WEA Texas Bayonne?
No public record read so far names a builder for WEA Texas Bayonne. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.