All industries › Data centers › Ohio › Aligned Data Center
Data centers · Erie County, Ohio
Aligned Data Center
A data center project in Erie County, Ohio. Aligned Data Center has work under way on site. Public records name Aligned Data Centers as its developer. No public record read so far names its builder.
The record
What the public record says about Aligned Data Center, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q2 2024 permit on file |
| Size | Not on record |
| Location | Erie County, Ohio (to about 10 km) |
| Developer | Aligned Data Centers |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also developed by Aligned Data Centers
| Project | Stage | Size |
|---|---|---|
| Aligned Data Center Chandler - Trade ParkingData centers · Arizona | Under construction | — |
| Aligned Data Center Chandler - Trade ParkingData centers · Arizona | Under construction | — |
| Aligned Data Center Memory Tech Phase 1 AdditionData centers · Collin County, Texas | Under construction | 11 acres |
| Aligned Data Centers (atl) PropcoData centers · Georgia | Under construction | — |
| Aligned Data Centers ORD03Data centers · Cook County, Illinois | Under construction | — |
| Aligned Plano DFW04Data centers · Collin County, Texas | Under construction | 40 acres |
Also in Erie County
| Project | Stage | Size |
|---|---|---|
| Unnamed 125 MW solar projectUtility solar | Queued | 125 MW |
| Wheatsborough SolarUtility solar | Operating | 125 MW |
More
Questions
Aligned Data Center, in short.
Where is Aligned Data Center?
Aligned Data Center is a data center project in Erie County, Ohio. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Aligned Data Center?
A construction permit on file dates the start of work to the second quarter of 2024.
Who is developing Aligned Data Center?
Aligned Data Centers, as the public record names it.
Who is building Aligned Data Center?
No public record read so far names a builder for Aligned Data Center. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.