All industries › Utility solar › Arizona › APS request Q401
Utility solar · Coconino County, Arizona
APS request Q401
A 700 MW utility solar project in Coconino County, Arizona. APS request Q401 has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. No public record read so far names its builder.
The record
What the public record says about APS request Q401, as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q1 2025 estimate |
| Size | 700 MW |
| Location | Coconino County, Arizona (to about 10 km) |
| Developer | Not named in any record read |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also in Coconino County
| Project | Stage | Size |
|---|---|---|
| CO Bar Solar and BESSUtility solar | Under construction | 400 MW |
| CO Bar D Solar and BESSUtility solar | Under construction | 394 MW |
| CO Bar C Solar and BESSUtility solar | Under construction | 206 MW |
| APS request Q255Utility solar | Queued | 2,000 MW |
| APS request Q274Utility solar | Queued | 1,000 MW |
| APS request Q317Utility solar | Queued | 750 MW |
More
Questions
APS request Q401, in short.
Where is APS request Q401?
APS request Q401 is a 700 MW utility solar project in Coconino County, Arizona. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on APS request Q401?
Groundtrace estimates construction starts in the first quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing APS request Q401?
No public record read so far names its developer.
Who is building APS request Q401?
No public record read so far names a builder for APS request Q401. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.