All industries › Battery storage › Texas › Blackland Prairie 1 Energy Storage

Battery storage illustration Battery storage · Travis County, Texas

Blackland Prairie 1 Energy Storage

A 102 MW battery storage project in Travis County, Texas. Blackland Prairie 1 Energy Storage has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name Balcones Ridge Resiliency LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Blackland Prairie 1 Energy Storage, as of 22 Oct 2026.

StageFinanced
Construction startQ4 2026 estimate
Size102 MW
LocationTravis County, Texas (to about 10 km)
DeveloperBalcones Ridge Resiliency LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also in Travis County

ProjectStageSize
East Blackland Battery Storage SLFBattery storageUnder construction75 MW
Austin Data Center 2Data centersUnder construction13 acres
Element Critical AUS1 Master Plan DesignData centersUnder construction11 acres
Giga Texas Data CenterBattery storageFinanced133 MW
Blackland Prairie 2 Energy StorageBattery storageQueued102 MW
Blackland Prairie 3 Energy StorageBattery storageQueued102 MW

Every project in Travis County

More

Questions

Blackland Prairie 1 Energy Storage, in short.

Where is Blackland Prairie 1 Energy Storage?

Blackland Prairie 1 Energy Storage is a 102 MW battery storage project in Travis County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Blackland Prairie 1 Energy Storage?

Groundtrace estimates construction starts in the fourth quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Blackland Prairie 1 Energy Storage?

Balcones Ridge Resiliency LLC, as the public record names it.

Who is building Blackland Prairie 1 Energy Storage?

No public record read so far names a builder for Blackland Prairie 1 Energy Storage. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.