All industries › Utility solar › Washington › Bluebird Solar

Utility solar illustration Utility solar · Klickitat County, Washington

Bluebird Solar

A 140 MW utility solar project in Klickitat County, Washington. Bluebird Solar has work under way on site. Public records name Avangrid Power LLC as its developer. A builder is on record; its name and the people to call are in the app.

The record

What the public record says about Bluebird Solar, as of 23 Oct 2026.

StageUnder construction
Construction startQ4 2025 permit on file
Size140 MW
LocationKlickitat County, Washington (to about 10 km)
DeveloperAvangrid Power LLC
Grid operator—
Builder (EPC) on record, in the app
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Avangrid Power LLC

ProjectStageSize
Great Bear SolarUtility solar · Van Wert County, OhioPre-construction46 MW
Allen Acres SolarUtility solar · LaSalle County, IllinoisQueued150 MW
Bright Mountain SolarUtility solar · Perry County, KentuckyQueued80 MW
Patriot Wind FarmOnshore wind · Nueces County, TexasOperating226 MW
Penascal II Wind ProjectOnshore wind · Kenedy County, TexasOperating202 MW
Penascal Wind PowerOnshore wind · Kenedy County, TexasOperating202 MW

Every Avangrid Power LLC project

Also in Klickitat County

ProjectStageSize
BPA request G0598Utility solarFinanced160 MW
BPA request G0608Battery storageQueued1,200 MW
BPA request G0932Utility solarQueued405 MW
BPA request G0933Utility solarQueued405 MW
BPA request G1016Utility solarQueued405 MW
BPA request G0589Utility solarQueued381 MW

Every project in Klickitat County

More

Questions

Bluebird Solar, in short.

Where is Bluebird Solar?

Bluebird Solar is a 140 MW utility solar project in Klickitat County, Washington. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Bluebird Solar?

A construction permit on file dates the start of work to the fourth quarter of 2025.

Who is developing Bluebird Solar?

Avangrid Power LLC, as the public record names it.

Who is building Bluebird Solar?

A builder is named for Bluebird Solar in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.