All industries › Utility solar › Oregon › Blueridge Solar/Battery Project
Utility solar · Morrow County, Oregon
Blueridge Solar/Battery Project
A 50 MW utility solar project in Morrow County, Oregon. Blueridge Solar/Battery Project is built and in service. Public records name Wheatridge Solar Energy Center, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Blueridge Solar/Battery Project, as of 1 Nov 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2022 |
| Size | 50 MW |
| Location | Morrow County, Oregon (to about 10 km) |
| Developer | Wheatridge Solar Energy Center, LLC |
| Grid operator | BPA |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also in Morrow County
| Project | Stage | Size |
|---|---|---|
| Wagon Trail Solar ProjectUtility solar | Under construction | 500 MW |
| Wheatridge Optimization IIUtility solar | Under construction | 130 MW |
| Wheatridge Optimization IUtility solar | Under construction | 110 MW |
| BPA request G0678Utility solar | Permitted | 1,200 MW |
| Wagon Trail Solar IIUtility solar | Permitted | 100 MW |
| Sunrise Solar and Storage ProjectsUtility solar | Queued | 800 MW |
More
Questions
Blueridge Solar/Battery Project, in short.
Where is Blueridge Solar/Battery Project?
Blueridge Solar/Battery Project is a 50 MW utility solar project in Morrow County, Oregon, in BPA's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Blueridge Solar/Battery Project?
Blueridge Solar/Battery Project is built and in service since 2022.
Who is developing Blueridge Solar/Battery Project?
Wheatridge Solar Energy Center, LLC, as the public record names it.
Who is building Blueridge Solar/Battery Project?
No public record read so far names a builder for Blueridge Solar/Battery Project. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.