All industries › Onshore wind › Wisconsin › Cedar Ridge
Onshore wind · Fond Du Lac County, Wisconsin
Cedar Ridge
A 68 MW onshore wind project in Fond Du Lac County, Wisconsin. Cedar Ridge is built and in service. Public records name Wisconsin Power & Light Co as its developer. No public record read so far names its builder.
The record
What the public record says about Cedar Ridge, as of 20 Nov 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2008 |
| Size | 68 MW |
| Location | Fond Du Lac County, Wisconsin (to about 10 km) |
| Developer | Wisconsin Power & Light Co |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Wisconsin Power & Light Co
| Project | Stage | Size |
|---|---|---|
| EdgewaterBattery storage · Sheboygan County, Wisconsin | Under construction | 99 MW |
| Unnamed 150 MW solar projectUtility solar · Columbia County, Wisconsin | Financed | 150 MW |
| Unnamed 100 MW solar projectUtility solar · Green County, Wisconsin | Financed | 100 MW |
| Unnamed 100 MW solar projectUtility solar · Winnebago County, Wisconsin | Financed | 100 MW |
| Unnamed 75 MW solar projectUtility solar · Sheboygan County, Wisconsin | Financed | 75 MW |
| Bent Tree Wind Farm Phase 1Onshore wind · Freeborn County, Minnesota | Operating | 201 MW |
Also in Fond Du Lac County
| Project | Stage | Size |
|---|---|---|
| Campbellsport Solar WIUtility solar | Pre-construction | 6 MW |
| Blue Sky Green Field Wind ProjectOnshore wind | Operating | 145 MW |
| Auburn Solar WIUtility solar | Operating | 5 MW |
| LedgeviewUtility solar | Operating | 5 MW |
| Nortera Customer Hosted SolarUtility solar | Operating | 2 MW |
| ENGIE 2020 ProjectCo-WI1Utility solar | Operating | 1 MW |
More
In your AI assistant
Ask it in Claude, ChatGPT or Cursor.
Connect Groundtrace once, and your assistant answers from the same public records: the builder, the construction dates and the source behind each fact.
Who is building Cedar Ridge in Fond Du Lac County, Wisconsin, and when does construction start?Questions
Cedar Ridge, in short.
Where is Cedar Ridge?
Cedar Ridge is a 68 MW onshore wind project in Fond Du Lac County, Wisconsin. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Cedar Ridge?
Cedar Ridge is built and in service since 2008.
Who is developing Cedar Ridge?
Wisconsin Power & Light Co, as the public record names it.
Who is building Cedar Ridge?
No public record read so far names a builder for Cedar Ridge. Groundtrace leaves the field empty and fills it when a permit, a filing or the builder's own page names one.
Start free
Open every project free: 500 credits a month, no card.
Every project and source, the builders and trade subcontractors on record and their construction dates, in the web app, the API or your AI assistant. Work contacts come with a paid plan.