A 100 acres data center project in Reeves County, Texas. Core Scientific has filed for the permits that come just before ground work, such as construction stormwater coverage. Public records name Core Scientific as its developer. No public record read so far names its builder.
The record
What the public record says about Core Scientific, as of 22 Oct 2026.
| Stage | Pre-construction |
|---|---|
| Construction start | Q1 2026 permit on file |
| Size | 100 acres |
| Location | Reeves County, Texas (to about 10 km) |
| Developer | Core Scientific |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Core Scientific
| Project | Stage | Size |
|---|---|---|
| Core Dalton 4Data centers · Whitfield County, Georgia | Under construction | — |
| Core Scientific Data Center ExpansionData centers · Denton County, Texas | Under construction | 96 acres |
| Core Scientific MarbleData centers · Cherokee County, North Carolina | Under construction | — |
| Core Scientific SiteData centers · Muskogee County, Oklahoma | Under construction | — |
| Core Scientific AUB1Data centers · Lee County, Alabama | Pre-construction | — |
| Core Scientific Gvt-1Data centers · Hunt County, Texas | Pre-construction | 50 acres |
Also in Reeves County
| Project | Stage | Size |
|---|---|---|
| Cantaloupe SolarUtility solar | Under construction | 307 MW |
| Alpha Digital CampusData centers | Pre-construction | 2,560 acres |
| August Draw SolarUtility solar | Financed | 250 MW |
| Bracero Pecan StorageBattery storage | Financed | 238 MW |
| Blue Heron BESSBattery storage | Financed | 201 MW |
| Nanulak BESSBattery storage | Financed | 182 MW |
More
Questions
Core Scientific, in short.
Where is Core Scientific?
Core Scientific is a 100 acres data center project in Reeves County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Core Scientific?
A construction permit on file dates the start of work to the first quarter of 2026.
Who is developing Core Scientific?
Core Scientific, as the public record names it.
Who is building Core Scientific?
No public record read so far names a builder for Core Scientific. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.