Crimson Orchard Solar and BESS
A 100 MW utility solar project in Elmore County, Idaho. Crimson Orchard Solar and BESS has work under way on site. Public records name Crimson Orchard Solar LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Crimson Orchard Solar and BESS, as of 20 Nov 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q1 2022 permit issued |
| Size | 100 MW |
| Location | Elmore County, Idaho (to about 10 km) |
| Developer | Crimson Orchard Solar LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Moved from under construction to financed.
- Satellite imagery shows first ground work on site.
- Clearing seen on site from satellite.
- Moved from financed to under construction.
- A filing dates the construction start to January 2022.
- Stormwater permit filed.
- Stormwater permit filed.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also in Elmore County
| Project | Stage | Size |
|---|---|---|
| IP request 667Utility solar | Financed | 400 MW |
| IP request 590Utility solar | Financed | 330 MW |
| IP request 551Utility solar | Financed | 240 MW |
| IP request 605Utility solar | Financed | 240 MW |
| IP request 636Utility solar | Financed | 149 MW |
| IP request 792Battery storage | Queued | 330 MW |
More
In your AI assistant
Ask it in Claude, ChatGPT or Cursor.
Connect Groundtrace once, and your assistant answers from the same public records: the builder, the construction dates and the source behind each fact.
Who is building Crimson Orchard Solar and BESS in Elmore County, Idaho, and when does construction start?Questions
Crimson Orchard Solar and BESS, in short.
Where is Crimson Orchard Solar and BESS?
Crimson Orchard Solar and BESS is a 100 MW utility solar project in Elmore County, Idaho. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Crimson Orchard Solar and BESS?
A permit on file dates the start of work to the first quarter of 2022.
Who is developing Crimson Orchard Solar and BESS?
Crimson Orchard Solar LLC, as the public record names it.
Who is building Crimson Orchard Solar and BESS?
No public record read so far names a builder for Crimson Orchard Solar and BESS. Groundtrace leaves the field empty and fills it when a permit, a filing or the builder's own page names one.
Start free