All industries › Data centers › Texas › DataBank DFW3
Data centers · Collin County, Texas
DataBank DFW3
A 16 acres data center project in Collin County, Texas. DataBank DFW3 has work under way on site. Public records name DataBank as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about DataBank DFW3, as of 23 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q1 2024 permit on file |
| Size | 16 acres |
| Location | Collin County, Texas (to about 10 km) |
| Developer | DataBank |
| Grid operator | — |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Air permit filed.
- Air permit filed.
- Stormwater permit filed.
- Stormwater permit filed.
Who was named on it, and when, is in the app.
Also developed by DataBank
| Project | Stage | Size |
|---|---|---|
| Culpeper DataBankData centers · Culpeper County, Virginia | Under construction | — |
| DataBankData centers · Johnson County, Kansas | Under construction | — |
| DataBank - Douglas CountyData centers · Douglas County, Colorado | Under construction | — |
| DataBank - GoldenData centers · Jefferson County, Colorado | Under construction | — |
| DataBank - Red OakData centers · Ellis County, Texas | Under construction | 217 acres |
| DataBank OrangeburgData centers · Rockland County, New York | Under construction | — |
Also in Collin County
| Project | Stage | Size |
|---|---|---|
| Mallard Energy StorageBattery storage | Under construction | 250 MW |
| Boxcar Energy StorageBattery storage | Under construction | 150 MW |
| Aligned Data Center Memory Tech Phase 1 AdditionData centers | Under construction | 11 acres |
| Aligned Plano DFW04Data centers | Under construction | 40 acres |
| CyrusOne DFW 4Data centers | Under construction | 12 acres |
| Drake BESSBattery storage | Financed | 257 MW |
More
Questions
DataBank DFW3, in short.
Where is DataBank DFW3?
DataBank DFW3 is a 16 acres data center project in Collin County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on DataBank DFW3?
A construction permit on file dates the start of work to the first quarter of 2024.
Who is developing DataBank DFW3?
DataBank, as the public record names it.
Who is building DataBank DFW3?
A builder is named for DataBank DFW3 in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.