All industries › Onshore wind › Texas › Electra Wind Farm
Onshore wind · Wilbarger County, Texas
Electra Wind Farm
A 230 MW onshore wind project in Wilbarger County, Texas. Electra Wind Farm is built and in service. Public records name Electra Wind, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Electra Wind Farm, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2016 |
| Size | 230 MW |
| Location | Wilbarger County, Texas (to about 10 km) |
| Developer | Electra Wind, LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Wilbarger County
| Project | Stage | Size |
|---|---|---|
| Adamstown SolarUtility solar | Under construction | 251 MW |
| Blue Summit Energy StorageBattery storage | Under construction | 100 MW |
| Felix North SolarUtility solar | Pre-construction | 201 MW |
| Felix East SolarUtility solar | Financed | 201 MW |
| Felix West SolarUtility solar | Financed | 201 MW |
| Dundee West WindOnshore wind | Financed | 146 MW |
More
Questions
Electra Wind Farm, in short.
Where is Electra Wind Farm?
Electra Wind Farm is a 230 MW onshore wind project in Wilbarger County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Electra Wind Farm?
Electra Wind Farm is built and in service since 2016.
Who is developing Electra Wind Farm?
Electra Wind, LLC, as the public record names it.
Who is building Electra Wind Farm?
No public record read so far names a builder for Electra Wind Farm. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.