Blue Summit Energy Storage

A 100 MW battery storage project in Wilbarger County, Texas. Blue Summit Energy Storage has work under way on site. Public records name NextEra Energy Interconnection Holdings, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Blue Summit Energy Storage, as of 23 Oct 2026.

StageUnder construction
Construction startQ4 2025 estimate
Size100 MW
LocationWilbarger County, Texas (to about 10 km)
DeveloperNextEra Energy Interconnection Holdings, LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by NextEra Energy Interconnection Holdings, LLC

ProjectStageSize
Bigway Solar IUtility solar · King County, TexasPre-construction195 MW
Half Moon SolarUtility solar · Starr County, TexasFinanced512 MW
Skyrider WindOnshore wind · Pecos County, TexasFinanced370 MW
Bob Creek WindOnshore wind · Sterling County, TexasFinanced239 MW
Bigway Solar IIUtility solar · King County, TexasFinanced206 MW
Varadero SolarUtility solar · Limestone County, TexasFinanced206 MW

Every NextEra Energy Interconnection Holdings, LLC project

Also in Wilbarger County

ProjectStageSize
Adamstown SolarUtility solarUnder construction251 MW
Felix North SolarUtility solarPre-construction201 MW
Felix East SolarUtility solarFinanced201 MW
Felix West SolarUtility solarFinanced201 MW
Dundee West WindOnshore windFinanced146 MW
Reunion SolarUtility solarQueued601 MW

Every project in Wilbarger County

More

Questions

Blue Summit Energy Storage, in short.

Where is Blue Summit Energy Storage?

Blue Summit Energy Storage is a 100 MW battery storage project in Wilbarger County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Blue Summit Energy Storage?

Groundtrace estimates construction started in the fourth quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Blue Summit Energy Storage?

NextEra Energy Interconnection Holdings, LLC, as the public record names it.

Who is building Blue Summit Energy Storage?

No public record read so far names a builder for Blue Summit Energy Storage. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.