All industries › Battery storage › Texas › Blue Summit Energy Storage
Battery storage · Wilbarger County, Texas
Blue Summit Energy Storage
A 100 MW battery storage project in Wilbarger County, Texas. Blue Summit Energy Storage has work under way on site. Public records name NextEra Energy Interconnection Holdings, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Blue Summit Energy Storage, as of 23 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q4 2025 estimate |
| Size | 100 MW |
| Location | Wilbarger County, Texas (to about 10 km) |
| Developer | NextEra Energy Interconnection Holdings, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by NextEra Energy Interconnection Holdings, LLC
| Project | Stage | Size |
|---|---|---|
| Bigway Solar IUtility solar · King County, Texas | Pre-construction | 195 MW |
| Half Moon SolarUtility solar · Starr County, Texas | Financed | 512 MW |
| Skyrider WindOnshore wind · Pecos County, Texas | Financed | 370 MW |
| Bob Creek WindOnshore wind · Sterling County, Texas | Financed | 239 MW |
| Bigway Solar IIUtility solar · King County, Texas | Financed | 206 MW |
| Varadero SolarUtility solar · Limestone County, Texas | Financed | 206 MW |
Also in Wilbarger County
| Project | Stage | Size |
|---|---|---|
| Adamstown SolarUtility solar | Under construction | 251 MW |
| Felix North SolarUtility solar | Pre-construction | 201 MW |
| Felix East SolarUtility solar | Financed | 201 MW |
| Felix West SolarUtility solar | Financed | 201 MW |
| Dundee West WindOnshore wind | Financed | 146 MW |
| Reunion SolarUtility solar | Queued | 601 MW |
More
Questions
Blue Summit Energy Storage, in short.
Where is Blue Summit Energy Storage?
Blue Summit Energy Storage is a 100 MW battery storage project in Wilbarger County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Blue Summit Energy Storage?
Groundtrace estimates construction started in the fourth quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Blue Summit Energy Storage?
NextEra Energy Interconnection Holdings, LLC, as the public record names it.
Who is building Blue Summit Energy Storage?
No public record read so far names a builder for Blue Summit Energy Storage. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.