A 195 MW utility solar project in King County, Texas. Bigway Solar I has filed for the permits that come just before ground work, such as construction stormwater coverage. Public records name NextEra Energy Interconnection Holdings, LLC as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Bigway Solar I, as of 22 Oct 2026.
| Stage | Pre-construction |
|---|---|
| Construction start | Q1 2026 permit on file |
| Size | 195 MW |
| Location | King County, Texas (to about 10 km) |
| Developer | NextEra Energy Interconnection Holdings, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by NextEra Energy Interconnection Holdings, LLC
| Project | Stage | Size |
|---|---|---|
| Blue Summit Energy StorageBattery storage · Wilbarger County, Texas | Under construction | 100 MW |
| Half Moon SolarUtility solar · Starr County, Texas | Financed | 512 MW |
| Skyrider WindOnshore wind · Pecos County, Texas | Financed | 370 MW |
| Bob Creek WindOnshore wind · Sterling County, Texas | Financed | 239 MW |
| Bigway Solar IIUtility solar · King County, Texas | Financed | 206 MW |
| Varadero SolarUtility solar · Limestone County, Texas | Financed | 206 MW |
Also in King County
| Project | Stage | Size |
|---|---|---|
| Bigway Solar IIUtility solar | Financed | 206 MW |
| White Oak King WindOnshore wind | Queued | 606 MW |
| WOE Gyp King WindOnshore wind | Queued | 304 MW |
More
Questions
Bigway Solar I, in short.
Where is Bigway Solar I?
Bigway Solar I is a 195 MW utility solar project in King County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Bigway Solar I?
A construction permit on file dates the start of work to the first quarter of 2026.
Who is developing Bigway Solar I?
NextEra Energy Interconnection Holdings, LLC, as the public record names it.
Who is building Bigway Solar I?
A builder is named for Bigway Solar I in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.