All industries › Utility solar › Texas › Silverton Solar
Utility solar · Briscoe County, Texas
Silverton Solar
A 410 MW utility solar project in Briscoe County, Texas. Silverton Solar has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name NextEra Energy Interconnection Holdings, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Silverton Solar, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q3 2027 estimate |
| Size | 410 MW |
| Location | Briscoe County, Texas (to about 10 km) |
| Developer | NextEra Energy Interconnection Holdings, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by NextEra Energy Interconnection Holdings, LLC
| Project | Stage | Size |
|---|---|---|
| Blue Summit Energy StorageBattery storage · Wilbarger County, Texas | Under construction | 100 MW |
| Bigway Solar IUtility solar · King County, Texas | Pre-construction | 195 MW |
| Half Moon SolarUtility solar · Starr County, Texas | Financed | 512 MW |
| Skyrider WindOnshore wind · Pecos County, Texas | Financed | 370 MW |
| Bob Creek WindOnshore wind · Sterling County, Texas | Financed | 239 MW |
| Bigway Solar IIUtility solar · King County, Texas | Financed | 206 MW |
Also in Briscoe County
| Project | Stage | Size |
|---|---|---|
| Commodus WindOnshore wind | Queued | 641 MW |
| Commodus SolarUtility solar | Queued | 502 MW |
| BRP Snowdon BESSBattery storage | Queued | 411 MW |
| Longhorn WindOnshore wind | Operating | 200 MW |
| Briscoe Wind FarmOnshore wind | Operating | 150 MW |
More
Questions
Silverton Solar, in short.
Where is Silverton Solar?
Silverton Solar is a 410 MW utility solar project in Briscoe County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Silverton Solar?
Groundtrace estimates construction starts in the third quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Silverton Solar?
NextEra Energy Interconnection Holdings, LLC, as the public record names it.
Who is building Silverton Solar?
No public record read so far names a builder for Silverton Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.