All industries › Data centers › Texas › Element Critical
Data centers · Harris County, Texas
Element Critical
A 0 acres data center project in Harris County, Texas. Element Critical has work under way on site. Public records name Element Critical as its developer. No public record read so far names its builder.
The record
What the public record says about Element Critical, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q4 2025 permit on file |
| Size | 0 acres |
| Location | Harris County, Texas (to about 10 km) |
| Developer | Element Critical |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also developed by Element Critical
| Project | Stage | Size |
|---|---|---|
| Element Critical AUS1 Master Plan DesignData centers · Travis County, Texas | Under construction | 11 acres |
Also in Harris County
| Project | Stage | Size |
|---|---|---|
| Beacon StorageBattery storage | Under construction | 409 MW |
| Sigma StorageBattery storage | Under construction | 408 MW |
| Callisto II Energy CenterBattery storage | Under construction | 203 MW |
| Kegans BESS (Houston IV BESS)Battery storage | Under construction | 165 MW |
| Pamela Heights IBattery storage | Under construction | 102 MW |
| BRIDGELAND PV SEC 36Utility solar | Under construction | 53 acres |
More
Questions
Element Critical, in short.
Where is Element Critical?
Element Critical is a 0 acres data center project in Harris County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Element Critical?
A construction permit on file dates the start of work to the fourth quarter of 2025.
Who is developing Element Critical?
Element Critical, as the public record names it.
Who is building Element Critical?
No public record read so far names a builder for Element Critical. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.