A 165 MW battery storage project in Harris County, Texas. Kegans BESS (Houston IV BESS) has work under way on site. Public records name SMT Houston IV LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Kegans BESS (Houston IV BESS), as of 23 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q3 2025 estimate |
| Size | 165 MW |
| Location | Harris County, Texas (to about 10 km) |
| Developer | SMT Houston IV LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Harris County
| Project | Stage | Size |
|---|---|---|
| Beacon StorageBattery storage | Under construction | 409 MW |
| Sigma StorageBattery storage | Under construction | 408 MW |
| Callisto II Energy CenterBattery storage | Under construction | 203 MW |
| Pamela Heights IBattery storage | Under construction | 102 MW |
| BRIDGELAND PV SEC 36Utility solar | Under construction | 53 acres |
| CyrusOne Houston Phase IIData centers | Under construction | 33 acres |
More
Questions
Kegans BESS (Houston IV BESS), in short.
Where is Kegans BESS (Houston IV BESS)?
Kegans BESS (Houston IV BESS) is a 165 MW battery storage project in Harris County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Kegans BESS (Houston IV BESS)?
Groundtrace estimates construction started in the third quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Kegans BESS (Houston IV BESS)?
SMT Houston IV LLC, as the public record names it.
Who is building Kegans BESS (Houston IV BESS)?
No public record read so far names a builder for Kegans BESS (Houston IV BESS). Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.