All industries › Utility solar › Texas › Felina
Utility solar · El Paso County, Texas
Felina
A 153 MW utility solar project in El Paso County, Texas. Felina is built and in service. Public records name El Paso Electric Co as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Felina, as of 23 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2025 |
| Size | 153 MW |
| Location | El Paso County, Texas (to about 10 km) |
| Developer | El Paso Electric Co |
| Grid operator | — |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by El Paso Electric Co
| Project | Stage | Size |
|---|---|---|
| Chihuahuan Desert SolarUtility solar · El Paso County, Texas | Operating | 10 MW |
| Holloman Solar FacilityUtility solar · Otero County, New Mexico | Operating | 5 MW |
| Montana Solar FacilityUtility solar · El Paso County, Texas | Operating | 3 MW |
| NMSU Solar and StorageUtility solar · Dona Ana County, New Mexico | Operating | 3 MW |
Also in El Paso County
| Project | Stage | Size |
|---|---|---|
| Evlou SolarUtility solar | Under construction | 250 MW |
| Oppidan El Paso Data CenterData centers | Under construction | 10 acres |
| DESERT PINE SOLARUtility solar | Pre-construction | 1,045 acres |
| TX200 COPPERHEAD PVUtility solar | Pre-construction | 901 acres |
| Chihuahuan Desert SolarUtility solar | Operating | 10 MW |
| Newman SolarUtility solar | Operating | 10 MW |
More
Questions
Felina, in short.
Where is Felina?
Felina is a 153 MW utility solar project in El Paso County, Texas. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Felina?
Felina is built and in service since 2025.
Who is developing Felina?
El Paso Electric Co, as the public record names it.
Who is building Felina?
A builder is named for Felina in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.