All industries › Utility solar › New Mexico › Holloman Solar Facility
Utility solar · Otero County, New Mexico
Holloman Solar Facility
A 5 MW utility solar project in Otero County, New Mexico. Holloman Solar Facility is built and in service. Public records name El Paso Electric Co as its developer. No public record read so far names its builder.
The record
What the public record says about Holloman Solar Facility, as of 23 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2018 |
| Size | 5 MW |
| Location | Otero County, New Mexico (to about 10 km) |
| Developer | El Paso Electric Co |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by El Paso Electric Co
| Project | Stage | Size |
|---|---|---|
| FelinaUtility solar · El Paso County, Texas | Operating | 153 MW |
| Chihuahuan Desert SolarUtility solar · El Paso County, Texas | Operating | 10 MW |
| Montana Solar FacilityUtility solar · El Paso County, Texas | Operating | 3 MW |
| NMSU Solar and StorageUtility solar · Dona Ana County, New Mexico | Operating | 3 MW |
Also in Otero County
| Project | Stage | Size |
|---|---|---|
| Buena Vista Energy Center IIIUtility solar | Under construction | 100 MW |
| AC120SB ProjectUtility solar | Financed | 120 MW |
| CO100SB ProjectUtility solar | Financed | 100 MW |
| TSGT request GI-DISIS-2021-04Utility solar | Financed | 100 MW |
| Iris Del SolUtility solar | Financed | 76 MW |
| Buena Vista Energy CenterUtility solar | Operating | 120 MW |
More
Questions
Holloman Solar Facility, in short.
Where is Holloman Solar Facility?
Holloman Solar Facility is a 5 MW utility solar project in Otero County, New Mexico. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Holloman Solar Facility?
Holloman Solar Facility is built and in service since 2018.
Who is developing Holloman Solar Facility?
El Paso Electric Co, as the public record names it.
Who is building Holloman Solar Facility?
No public record read so far names a builder for Holloman Solar Facility. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.