All industries › Utility solar › Illinois › Four Mile Creek
Utility solar · Jefferson County, Illinois
Four Mile Creek
A 5 MW utility solar project in Jefferson County, Illinois. Four Mile Creek has work under way on site. Public records name Four Mile Creek Solar, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Four Mile Creek, as of 24 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q3 2025 estimate |
| Size | 5 MW |
| Location | Jefferson County, Illinois (to about 10 km) |
| Developer | Four Mile Creek Solar, LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also in Jefferson County
| Project | Stage | Size |
|---|---|---|
| Harper Creek SolarUtility solar | Under construction | 5 MW |
| Unnamed 200 MW solar projectUtility solar | Financed | 200 MW |
| Unnamed 200 MW storage projectBattery storage | Queued | 200 MW |
| Casey Fork SolarUtility solar | Operating | 150 MW |
| Marlow Solar, LLC CSGUtility solar | Operating | 2 MW |
More
Questions
Four Mile Creek, in short.
Where is Four Mile Creek?
Four Mile Creek is a 5 MW utility solar project in Jefferson County, Illinois. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Four Mile Creek?
Groundtrace estimates construction started in the third quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Four Mile Creek?
Four Mile Creek Solar, LLC, as the public record names it.
Who is building Four Mile Creek?
No public record read so far names a builder for Four Mile Creek. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.