All industries › Utility solar › Iowa › Franklin County Solar
Utility solar · Franklin County, Iowa
Franklin County Solar
A 7 MW utility solar project in Franklin County, Iowa. Franklin County Solar is built and in service. Public records name MidAmerican Energy Co as its developer. No public record read so far names its builder.
The record
What the public record says about Franklin County Solar, as of 23 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2022 |
| Size | 7 MW |
| Location | Franklin County, Iowa (to about 10 km) |
| Developer | MidAmerican Energy Co |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by MidAmerican Energy Co
| Project | Stage | Size |
|---|---|---|
| Mills Solar ProjectUtility solar · Mills County, Iowa | Under construction | 50 MW |
| Highland Wind Project (IA)Onshore wind · O'Brien County, Iowa | Operating | 502 MW |
| Orient Wind FarmOnshore wind · Adair County, Iowa | Operating | 501 MW |
| Rolling Hills Wind FarmOnshore wind · Cass County, Iowa | Operating | 484 MW |
| Beaver Creek WindOnshore wind · Boone County, Iowa | Operating | 340 MW |
| North EnglishOnshore wind · Poweshiek County, Iowa | Operating | 340 MW |
Also in Franklin County
| Project | Stage | Size |
|---|---|---|
| Unnamed 200 MW wind projectOnshore wind | Queued | 200 MW |
| Unnamed 200 MW storage projectBattery storage | Queued | 200 MW |
| Whispering Willow NorthOnshore wind | Operating | 201 MW |
| Whispering Willow Wind Farm - EastOnshore wind | Operating | 200 MW |
| Franklin County Wind FarmOnshore wind | Operating | 99 MW |
| Hampton Substation Energy StorageBattery storage | Operating | 2 MW |
More
Questions
Franklin County Solar, in short.
Where is Franklin County Solar?
Franklin County Solar is a 7 MW utility solar project in Franklin County, Iowa. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Franklin County Solar?
Franklin County Solar is built and in service since 2022.
Who is developing Franklin County Solar?
MidAmerican Energy Co, as the public record names it.
Who is building Franklin County Solar?
No public record read so far names a builder for Franklin County Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.