All industries › Utility solar › New York › Homer Solar Energy Center
Utility solar · Cortland County, New York
Homer Solar Energy Center
A 90 MW utility solar project in Cortland County, New York. Homer Solar Energy Center has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. No public record read so far names its builder.
The record
What the public record says about Homer Solar Energy Center, as of 23 Oct 2026.
| Stage | Financed |
|---|---|
| Construction start | Q2 2026 estimate |
| Size | 90 MW |
| Location | Cortland County, New York (to about 10 km) |
| Developer | Not named in any record read |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also in Cortland County
| Project | Stage | Size |
|---|---|---|
| Cortland CSG 2Utility solar | Under construction | 5 MW |
| NY8 - Janis SolarUtility solar | Operating | 20 MW |
| Bellisario Solar 1Utility solar | Operating | 5 MW |
| Bellisario Solar 2Utility solar | Operating | 5 MW |
| Bellisario Solar 3Utility solar | Operating | 5 MW |
| CortlandvilleUtility solar | Operating | 5 MW |
More
Questions
Homer Solar Energy Center, in short.
Where is Homer Solar Energy Center?
Homer Solar Energy Center is a 90 MW utility solar project in Cortland County, New York. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Homer Solar Energy Center?
Groundtrace estimates construction starts in the second quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Homer Solar Energy Center?
No public record read so far names its developer.
Who is building Homer Solar Energy Center?
No public record read so far names a builder for Homer Solar Energy Center. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.