A 285 MW utility solar project in Millard County, Utah. LADWP request Q53 has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Intermountain Power Agency as its developer. No public record read so far names its builder.
The record
What the public record says about LADWP request Q53, as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Not dated or estimated yet |
| Size | 285 MW |
| Location | Millard County, Utah (to about 10 km) |
| Developer | Intermountain Power Agency |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Entered the public record for the first time.
Who was named on it, and when, is in the app.
Also developed by Intermountain Power Agency
| Project | Stage | Size |
|---|---|---|
| LADWP request Q93Utility solar · Millard County, Utah | Queued | 1,000 MW |
| LADWP request Q105Utility solar · Millard County, Utah | Queued | 600 MW |
| LADWP request Q104Utility solar · Millard County, Utah | Queued | 400 MW |
| LADWP request Q50Utility solar · Millard County, Utah | Queued | 400 MW |
| LADWP request Q51Utility solar · Millard County, Utah | Queued | 400 MW |
| LADWP request Q90Utility solar · Millard County, Utah | Queued | 400 MW |
Also in Millard County
| Project | Stage | Size |
|---|---|---|
| Joule Capital Partners, LLC - Site #1 Data CenterData centers | Under construction | — |
| Notch Peak SolarUtility solar | Pre-construction | 324 MW |
| LADWP request Q93Utility solar | Queued | 1,000 MW |
| LADWP request Q105Utility solar | Queued | 600 MW |
| PacifiCorp request C3-036Utility solar | Queued | 500 MW |
| LADWP request Q104Utility solar | Queued | 400 MW |
More
Questions
LADWP request Q53, in short.
Where is LADWP request Q53?
LADWP request Q53 is a 285 MW utility solar project in Millard County, Utah. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on LADWP request Q53?
No record dates the construction start yet, and Groundtrace has not estimated one.
Who is developing LADWP request Q53?
Intermountain Power Agency, as the public record names it.
Who is building LADWP request Q53?
No public record read so far names a builder for LADWP request Q53. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.