All industries › Utility solar › Georgia › Lowndes IDA
Utility solar · Lowndes County, Georgia
Lowndes IDA
A 2 MW utility solar project in Lowndes County, Georgia. Lowndes IDA is built and in service. Public records name Safari Energy, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Lowndes IDA, as of 23 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2020 |
| Size | 2 MW |
| Location | Lowndes County, Georgia (to about 10 km) |
| Developer | Safari Energy, LLC |
| Grid operator | — |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Safari Energy, LLC
| Project | Stage | Size |
|---|---|---|
| Bulloch Neville FarmsUtility solar · Bulloch County, Georgia | Operating | 3 MW |
| Franklin MillikenUtility solar · Franklin County, Georgia | Operating | 3 MW |
| Greene DurhamUtility solar · Greene County, Georgia | Operating | 3 MW |
| Meriwether JacksonUtility solar · Meriwether County, Georgia | Operating | 3 MW |
| Murray Treadwell FarmsUtility solar · Murray County, Georgia | Operating | 3 MW |
| Polk County GA S1Utility solar · Polk County, Georgia | Operating | 3 MW |
Also in Lowndes County
| Project | Stage | Size |
|---|---|---|
| Moody Air Force Base SolarUtility solar | Operating | 50 MW |
| Lowndes CowartUtility solar | Operating | 3 MW |
| Lowndes Tycor FarmsUtility solar | Operating | 2 MW |
| Valdosta (Terraform)Utility solar | Operating | 1 MW |
| Valdosta PrisonUtility solar | Operating | 1 MW |
More
Questions
Lowndes IDA, in short.
Where is Lowndes IDA?
Lowndes IDA is a 2 MW utility solar project in Lowndes County, Georgia. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Lowndes IDA?
Lowndes IDA is built and in service since 2020.
Who is developing Lowndes IDA?
Safari Energy, LLC, as the public record names it.
Who is building Lowndes IDA?
No public record read so far names a builder for Lowndes IDA. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.