All industries › Utility solar › North Carolina › Midfield Solar

Utility solar illustration Utility solar · Columbus County, North Carolina

Midfield Solar

A 25 MW utility solar project in Columbus County, North Carolina. Midfield Solar has work under way on site. Public records name Headwater Energy, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Midfield Solar, as of 23 Oct 2026.

StageUnder construction
Construction startQ4 2025 permit on file
Size25 MW
LocationColumbus County, North Carolina (to about 10 km)
DeveloperHeadwater Energy, LLC
Grid operator—
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Headwater Energy, LLC

ProjectStageSize
Gum Swamp SolarUtility solar · Scotland County, North CarolinaUnder construction80 MW
Sleepy Creek SolarUtility solar · Bladen County, North CarolinaUnder construction80 MW
Westfield SolarUtility solar · Hoke County, North CarolinaUnder construction40 MW
Tanglewood SolarUtility solar · Pasquotank County, North CarolinaUnder construction8 MW
Bishopville SolarUtility solar · Lee County, South CarolinaOperating20 MW
Ebbie SolarUtility solar · Marion County, South CarolinaOperating10 MW

Every Headwater Energy, LLC project

Also in Columbus County

ProjectStageSize
Duke request 977914Utility solarQueued80 MW
Acme SolarUtility solarOperating5 MW
Arthur 2 SolarUtility solarOperating5 MW
Arthur SolarUtility solarOperating5 MW
Beckwith SolarUtility solarOperating5 MW
Broadway Solar CenterUtility solarOperating5 MW

More

Questions

Midfield Solar, in short.

Where is Midfield Solar?

Midfield Solar is a 25 MW utility solar project in Columbus County, North Carolina. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Midfield Solar?

A construction permit on file dates the start of work to the fourth quarter of 2025.

Who is developing Midfield Solar?

Headwater Energy, LLC, as the public record names it.

Who is building Midfield Solar?

No public record read so far names a builder for Midfield Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.