All industries › Utility solar › Arkansas › Unnamed 250 MW solar project
Utility solar · Union County, Arkansas
Unnamed 250 MW solar project
A 250 MW utility solar project in Union County, Arkansas. Unnamed 250 MW solar project has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. No public record read so far names its builder.
The record
What the public record says about Unnamed 250 MW solar project, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q1 2027 estimate |
| Size | 250 MW |
| Location | Union County, Arkansas (to about 10 km) |
| Developer | Not named in any record read |
| Grid operator | MISO |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Union County
| Project | Stage | Size |
|---|---|---|
| Unnamed 100 MW solar projectUtility solar | Under construction | 100 MW |
| Unnamed 250 MW solar projectUtility solar | Queued | 250 MW |
| Unnamed 100 MW storage projectBattery storage | Queued | 100 MW |
| El Dorado ARUtility solar | Operating | 2 MW |
More
Questions
Unnamed 250 MW solar project, in short.
Where is Unnamed 250 MW solar project?
Unnamed 250 MW solar project is a 250 MW utility solar project in Union County, Arkansas, in MISO's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Unnamed 250 MW solar project?
Groundtrace estimates construction starts in the first quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Unnamed 250 MW solar project?
No public record read so far names its developer.
Who is building Unnamed 250 MW solar project?
No public record read so far names a builder for Unnamed 250 MW solar project. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.