All industries › Battery storage › Michigan › Unnamed 500 MW storage project
Battery storage · Huron County, Michigan
Unnamed 500 MW storage project
A 500 MW battery storage project in Huron County, Michigan. Unnamed 500 MW storage project has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. No public record read so far names its builder.
The record
What the public record says about Unnamed 500 MW storage project, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Not dated or estimated yet |
| Size | 500 MW |
| Location | Huron County, Michigan (to about 10 km) |
| Developer | Not named in any record read |
| Grid operator | MISO |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Huron County
| Project | Stage | Size |
|---|---|---|
| Silver Creek Solar ParkUtility solar | Under construction | 200 MW |
| Unnamed 200 MW storage projectBattery storage | Financed | 200 MW |
| Unnamed 300 MW storage projectBattery storage | Queued | 300 MW |
| Unnamed 300 MW storage projectBattery storage | Queued | 300 MW |
| Unnamed 250 MW storage projectBattery storage | Queued | 250 MW |
| Unnamed 250 MW storage projectBattery storage | Queued | 250 MW |
More
Questions
Unnamed 500 MW storage project, in short.
Where is Unnamed 500 MW storage project?
Unnamed 500 MW storage project is a 500 MW battery storage project in Huron County, Michigan, in MISO's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Unnamed 500 MW storage project?
No record dates the construction start yet, and Groundtrace has not estimated one.
Who is developing Unnamed 500 MW storage project?
No public record read so far names its developer.
Who is building Unnamed 500 MW storage project?
No public record read so far names a builder for Unnamed 500 MW storage project. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.