All industries › Utility solar › Texas › MRG GOODY SOLAR
Utility solar · Lamar County, Texas
MRG GOODY SOLAR
A 171 MW utility solar project in Lamar County, Texas. MRG GOODY SOLAR has work under way on site. Public records name MRG GOODY SOLAR PROJECT, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about MRG GOODY SOLAR, as of 25 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q1 2025 estimate |
| Size | 171 MW |
| Location | Lamar County, Texas (to about 10 km) |
| Developer | MRG GOODY SOLAR PROJECT, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by MRG GOODY SOLAR PROJECT, LLC
| Project | Stage | Size |
|---|---|---|
| MRG Goody StorageBattery storage · Lamar County, Texas | Under construction | 52 MW |
Also in Lamar County
| Project | Stage | Size |
|---|---|---|
| Baker Branch SolarUtility solar | Under construction | 469 MW |
| Rowdy Creek SolarUtility solar | Under construction | 352 MW |
| Delilah Solar 2Utility solar | Under construction | 318 MW |
| Delilah Solar 1Utility solar | Under construction | 300 MW |
| Samson Solar 1Utility solar | Under construction | 250 MW |
| Star Dairy StorageBattery storage | Under construction | 205 MW |
More
Questions
MRG GOODY SOLAR, in short.
Where is MRG GOODY SOLAR?
MRG GOODY SOLAR is a 171 MW utility solar project in Lamar County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on MRG GOODY SOLAR?
Groundtrace estimates construction started in the first quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing MRG GOODY SOLAR?
MRG GOODY SOLAR PROJECT, LLC, as the public record names it.
Who is building MRG GOODY SOLAR?
No public record read so far names a builder for MRG GOODY SOLAR. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.