Mustang Creek Solar
A 150 MW utility solar project in Jackson County, Texas. Mustang Creek Solar is built and in service. Public records name Ganado Solar, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Mustang Creek Solar, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2023 |
| Size | 150 MW |
| Location | Jackson County, Texas (to about 10 km) |
| Developer | Ganado Solar, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Jackson County
| Project | Stage | Size |
|---|---|---|
| New Hickory SolarUtility solar | Under construction | 209 MW |
| Dios BESSBattery storage | Financed | 201 MW |
| Third Coast BESSBattery storage | Financed | 103 MW |
| Sayle Solar SLFUtility solar | Queued | 122 MW |
| Sayle Storage SLFBattery storage | Queued | 122 MW |
| Texas Sun SolarUtility solar | Queued | 72 MW |
More
Questions
Mustang Creek Solar, in short.
Where is Mustang Creek Solar?
Mustang Creek Solar is a 150 MW utility solar project in Jackson County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Mustang Creek Solar?
Mustang Creek Solar is built and in service since 2023.
Who is developing Mustang Creek Solar?
Ganado Solar, LLC, as the public record names it.
Who is building Mustang Creek Solar?
No public record read so far names a builder for Mustang Creek Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.