All industries › Battery storage › Texas › Myers Storage
Battery storage · Bee County, Texas
Myers Storage
A 76 MW battery storage project in Bee County, Texas. Myers Storage has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name BT Myers Solar, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Myers Storage, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q3 2027 estimate |
| Size | 76 MW |
| Location | Bee County, Texas (to about 10 km) |
| Developer | BT Myers Solar, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by BT Myers Solar, LLC
| Project | Stage | Size |
|---|---|---|
| Myers SolarUtility solar · Bee County, Texas | Queued | 102 MW |
Also in Bee County
| Project | Stage | Size |
|---|---|---|
| Foxtrot WindOnshore wind | Under construction | 268 MW |
| Honeycomb Solar SLFUtility solar | Under construction | 61 MW |
| Argenta SolarUtility solar | Financed | 310 MW |
| Abeja Solar FarmUtility solar | Financed | 201 MW |
| Argenta StorageBattery storage | Financed | 192 MW |
| Sparta BESSBattery storage | Queued | 251 MW |
More
Questions
Myers Storage, in short.
Where is Myers Storage?
Myers Storage is a 76 MW battery storage project in Bee County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Myers Storage?
Groundtrace estimates construction starts in the third quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Myers Storage?
BT Myers Solar, LLC, as the public record names it.
Who is building Myers Storage?
No public record read so far names a builder for Myers Storage. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.