All industries › Utility solar › Ohio › Unnamed 800 MW solar project

Utility solar illustration Utility solar · Clermont County, Ohio

Unnamed 800 MW solar project

A 800 MW utility solar project in Clermont County, Ohio. Unnamed 800 MW solar project has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. No public record read so far names its builder.

The record

What the public record says about Unnamed 800 MW solar project, as of 25 Oct 2026.

StageQueued
Construction startQ4 2026 estimate
Size800 MW
LocationClermont County, Ohio (to about 10 km)
DeveloperNot named in any record read
Grid operatorPJM
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also in Clermont County

ProjectStageSize
Clermont County Solar ProjectUtility solarPermitted100 MW
Unnamed 250 MW storage projectBattery storageQueued250 MW
Clermont County Solar ProjectBattery storageQueued152 MW
Unnamed 152 MW solar projectUtility solarQueued152 MW
Unnamed 84 MW solar projectUtility solarQueued84 MW
Nestlewood SolarUtility solarOperating80 MW

Every project in Clermont County

More

Questions

Unnamed 800 MW solar project, in short.

Where is Unnamed 800 MW solar project?

Unnamed 800 MW solar project is a 800 MW utility solar project in Clermont County, Ohio, in PJM's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Unnamed 800 MW solar project?

Groundtrace estimates construction starts in the fourth quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Unnamed 800 MW solar project?

No public record read so far names its developer.

Who is building Unnamed 800 MW solar project?

No public record read so far names a builder for Unnamed 800 MW solar project. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $1,500 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.