All industries › Utility solar › Ohio › Sycamore Creek Solar
Utility solar · Crawford County, Ohio
Sycamore Creek Solar
A 117 MW utility solar project in Crawford County, Ohio. Sycamore Creek Solar is built and in service. Public records name Geronimo Power as its developer. No public record read so far names its builder.
The record
What the public record says about Sycamore Creek Solar, as of 25 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2025 |
| Size | 117 MW |
| Location | Crawford County, Ohio (to about 10 km) |
| Developer | Geronimo Power |
| Grid operator | PJM |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Geronimo Power
| Project | Stage | Size |
|---|---|---|
| Portage SolarUtility solar · Portage County, Wisconsin | Under construction | 250 MW |
| Bee Hollow SolarUtility solar · St Clair County, Illinois | Under construction | 150 MW |
| Grant SolarUtility solar · McCook County, South Dakota | Pre-construction | 99 MW |
| Yellowbud SolarUtility solar · Ross County, Ohio | Operating | 274 MW |
| Prairie Wolf SolarUtility solar · Coles County, Illinois | Operating | 200 MW |
| Unbridled SolarUtility solar · Henderson County, Kentucky | Operating | 160 MW |
Also in Crawford County
| Project | Stage | Size |
|---|---|---|
| EDP Renewable Lincoln/Bucyrus Solar SiteUtility solar | Under construction | — |
| Unnamed 430 MW solar projectUtility solar | Queued | 430 MW |
| Unnamed 400 MW solar projectUtility solar | Queued | 400 MW |
| Unnamed 117 MW solar projectUtility solar | Queued | 117 MW |
| Unnamed 85 MW solar projectUtility solar | Queued | 85 MW |
| Unnamed 50 MW solar projectUtility solar | Queued | 50 MW |
More
Questions
Sycamore Creek Solar, in short.
Where is Sycamore Creek Solar?
Sycamore Creek Solar is a 117 MW utility solar project in Crawford County, Ohio, in PJM's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Sycamore Creek Solar?
Sycamore Creek Solar is built and in service since 2025.
Who is developing Sycamore Creek Solar?
Geronimo Power, as the public record names it.
Who is building Sycamore Creek Solar?
No public record read so far names a builder for Sycamore Creek Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $1,500 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.