All industries › Onshore wind › Texas › Vista Bluff Wind I "Alternate POI"
Onshore wind · Upton County, Texas
Vista Bluff Wind I "Alternate POI"
A 290 MW onshore wind project in Upton County, Texas. Vista Bluff Wind I "Alternate POI" has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Vista Bluff Windpower, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Vista Bluff Wind I "Alternate POI", as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q3 2028 estimate |
| Size | 290 MW |
| Location | Upton County, Texas (to about 10 km) |
| Developer | Vista Bluff Windpower, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Vista Bluff Windpower, LLC
| Project | Stage | Size |
|---|---|---|
| Vista Bluff Wind II "Alternate POI"Onshore wind · Upton County, Texas | Queued | 290 MW |
Also in Upton County
| Project | Stage | Size |
|---|---|---|
| McCamey's Castle BatteryBattery storage | Under construction | 410 MW |
| Grandfalls SolarUtility solar | Under construction | 176 MW |
| Grandfalls Storage SLFBattery storage | Under construction | 176 MW |
| King Mountain SolarUtility solar | Under construction | 175 MW |
| Tres Rios Ranch SolarUtility solar | Financed | 508 MW |
| Tres Rios Ranch BESSBattery storage | Financed | 290 MW |
More
Questions
Vista Bluff Wind I "Alternate POI", in short.
Where is Vista Bluff Wind I "Alternate POI"?
Vista Bluff Wind I "Alternate POI" is a 290 MW onshore wind project in Upton County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Vista Bluff Wind I "Alternate POI"?
Groundtrace estimates construction starts in the third quarter of 2028. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Vista Bluff Wind I "Alternate POI"?
Vista Bluff Windpower, LLC, as the public record names it.
Who is building Vista Bluff Wind I "Alternate POI"?
No public record read so far names a builder for Vista Bluff Wind I "Alternate POI". Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.