All industries › Onshore wind › Texas › Vista Bluff Wind I "Alternate POI"

Onshore wind illustration Onshore wind · Upton County, Texas

Vista Bluff Wind I "Alternate POI"

A 290 MW onshore wind project in Upton County, Texas. Vista Bluff Wind I "Alternate POI" has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Vista Bluff Windpower, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Vista Bluff Wind I "Alternate POI", as of 22 Oct 2026.

StageQueued
Construction startQ3 2028 estimate
Size290 MW
LocationUpton County, Texas (to about 10 km)
DeveloperVista Bluff Windpower, LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Vista Bluff Windpower, LLC

ProjectStageSize
Vista Bluff Wind II "Alternate POI"Onshore wind · Upton County, TexasQueued290 MW

Every Vista Bluff Windpower, LLC project

Also in Upton County

ProjectStageSize
McCamey's Castle BatteryBattery storageUnder construction410 MW
Grandfalls SolarUtility solarUnder construction176 MW
Grandfalls Storage SLFBattery storageUnder construction176 MW
King Mountain SolarUtility solarUnder construction175 MW
Tres Rios Ranch SolarUtility solarFinanced508 MW
Tres Rios Ranch BESSBattery storageFinanced290 MW

Every project in Upton County

More

Questions

Vista Bluff Wind I "Alternate POI", in short.

Where is Vista Bluff Wind I "Alternate POI"?

Vista Bluff Wind I "Alternate POI" is a 290 MW onshore wind project in Upton County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Vista Bluff Wind I "Alternate POI"?

Groundtrace estimates construction starts in the third quarter of 2028. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Vista Bluff Wind I "Alternate POI"?

Vista Bluff Windpower, LLC, as the public record names it.

Who is building Vista Bluff Wind I "Alternate POI"?

No public record read so far names a builder for Vista Bluff Wind I "Alternate POI". Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.