All industries › Utility solar › Texas › Wagyu Solar

Utility solar illustration Utility solar · Brazoria County, Texas

Wagyu Solar

A 120 MW utility solar project in Brazoria County, Texas. Wagyu Solar is built and in service. Public records name Cypress Creek Renewables as its developer. A builder is on record; its name and the people to call are in the app.

The record

What the public record says about Wagyu Solar, as of 25 Oct 2026.

StageOperating
Construction startIn service since 2020
Size120 MW
LocationBrazoria County, Texas (to about 10 km)
DeveloperCypress Creek Renewables
Grid operatorERCOT
Builder (EPC) on record, in the app
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

  1. Entered the public record for the first time.

Who was named on it, and when, is in the app.

Also developed by Cypress Creek Renewables

ProjectStageSize
Steel River Solar Phase 1Utility solar · Mississippi County, ArkansasUnder construction500 MW
Steel River Solar Phase 2Utility solar · Mississippi County, ArkansasUnder construction500 MW
Steel River Solar Phase 3Utility solar · Mississippi County, ArkansasUnder construction500 MW
South DavidsonUtility solar · Davidson County, North CarolinaUnder construction80 MW
Sundance (CO)Utility solar · Elbert County, ColoradoUnder construction75 MW
Healing Springs SolarUtility solar · Davidson County, North CarolinaUnder construction55 MW

Every Cypress Creek Renewables project

Also in Brazoria County

ProjectStageSize
Cottonwood Bayou SolarUtility solarUnder construction351 MW
Myrtle SolarUtility solarUnder construction321 MW
Tanglewood SolarUtility solarUnder construction251 MW
Brazoria Solar IUtility solarUnder construction250 MW
Cradle SolarUtility solarUnder construction201 MW
CastorBattery storageUnder construction200 MW

Every project in Brazoria County

More

Questions

Wagyu Solar, in short.

Where is Wagyu Solar?

Wagyu Solar is a 120 MW utility solar project in Brazoria County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Wagyu Solar?

Wagyu Solar is built and in service since 2020.

Who is developing Wagyu Solar?

Cypress Creek Renewables, as the public record names it.

Who is building Wagyu Solar?

A builder is named for Wagyu Solar in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $1,500 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.