Ford County, Kansas
2 utility solar, 2 battery storage and 1 onshore wind projects are in development in Ford County, 1 of them under construction, with 7 more already operating. The solar, battery storage and wind projects in development add up to 627 MW. Who is building each one, and who to call, is in the app.
By industry
What is in development in Ford County, and each industry’s page for Kansas.
Next to break ground
Projects here among the ones in Kansas most likely to start work next.
- Unnamed 50 MW storage projectFord CountyFinanced · 50 MW · start est. 2027 Q4Builder: not yet named
In development
Every project in development in Ford County.
Nearest to work first: under construction, then pre-construction, financed, permitted and queued. A project on a county line is listed in each county.
| Project | Stage | Size |
|---|---|---|
| Unnamed 252 MW wind projectOnshore wind | Under construction | 252 MW |
| Unnamed 150 MW solar projectUtility solar | Financed | 150 MW |
| Unnamed 100 MW solar projectUtility solar | Financed | 100 MW |
| Unnamed 50 MW storage projectBattery storage | Financed | 50 MW |
| Boot Hill Energy StorageBattery storage | Permitted | 75 MW |
Builders, developers, construction starts and the people to call, for every project here.
Request access7 operating projects in Ford County
- Iron Star Wind ProjectOnshore wind · 298 MW
- Western Plains Wind FarmOnshore wind · 281 MW
- Bloom WindOnshore wind · 178 MW
- Ironwood WindOnshore wind · 168 MW
- SPP queue GEN-2023-SR28Utility solar · 150 MW
- SpearvilleOnshore wind · 148 MW
- Spearville 3 LLCOnshore wind · 108 MW
Nearby in Kansas
Also in Kansas
Questions
Ford County, in short.
How many projects are in development in Ford County, Kansas?
2 utility solar, 2 battery storage and 1 onshore wind projects are in development in Ford County, 1 of them under construction, with 7 more already operating.
Which projects in Ford County, Kansas are under construction?
Unnamed 252 MW wind project (252 MW).
Where does the Ford County data come from?
From the public records read daily for Kansas: grid interconnection queues, construction permits, county records, state siting and procurement filings, and satellite imagery. Locations are shown to a tenth of a degree; builders, developers, construction starts and work contacts are in the subscriber record.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- How it works
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.