A 393 MW onshore wind project in Haskell County, Texas. Apogee Wind is built and in service. Public records name EDF Renewables Development, Inc. as its developer. No public record read so far names its builder.
The record
What the public record says about Apogee Wind, as of 23 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2024 |
| Size | 393 MW |
| Location | Haskell County, Texas (to about 10 km) |
| Developer | EDF Renewables Development, Inc. |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by EDF Renewables Development, Inc.
| Project | Stage | Size |
|---|---|---|
| LYCAN SOLARUtility solar · Riverside County, California | Financed | 400 MW |
| BONANZA SOLARUtility solar · Clark County / Nye County, Nevada | Financed | 300 MW |
| Eastern Cottontail SolarUtility solar · Fairfield County, Ohio | Permitted | 220 MW |
| Rock House SolarUtility solar · Mcduffie County, Georgia | Queued | 250 MW |
| Sawtooth SolarUtility solar · Pinal County, Arizona | Queued | 250 MW |
| Voyager StorageBattery storage · Wharton County, Texas | Queued | 50 MW |
Also in Haskell County
| Project | Stage | Size |
|---|---|---|
| Quantum II BESSBattery storage | Under construction | 422 MW |
| Quantum II SolarUtility solar | Under construction | 363 MW |
| Quantum SolarUtility solar | Under construction | 322 MW |
| Quantum StorageBattery storage | Under construction | 322 MW |
| Solace SolarUtility solar | Under construction | 322 MW |
| Solace StorageBattery storage | Under construction | 322 MW |
More
Questions
Apogee Wind, in short.
Where is Apogee Wind?
Apogee Wind is a 393 MW onshore wind project in Haskell County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Apogee Wind?
Apogee Wind is built and in service since 2024.
Who is developing Apogee Wind?
EDF Renewables Development, Inc., as the public record names it.
Who is building Apogee Wind?
No public record read so far names a builder for Apogee Wind. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.